加纳达瓦100MW光伏项目电控系统采购

加纳达瓦100MW光伏项目电控系统采购

加纳达瓦100MW光伏项目电控系统采购
项目编号:****点击查看
发布时间:2026-06-05 09:33:22
补遗公告
公告标题:二次技术规范书
公告内容:

原技术规范书缺少34.5送出线路保护配置方案,现补全,由于业主电网研究报告延迟,线路保护配置方案我们按照两个方案进行配置,在定标前,我们会具体的配置方案,目前请二次厂家按照两套方案进行配置(详见最新的技术规范书),详见附件。现已补充图纸,有任何疑问及时进行澄清工作。

6

34.5 kV section

6.1

34.5 kV line protection and measurement control device

Set

4

2 sets for 1# outgoing feeder, 2 sets for 2# outgoing feeder(Note: The protection type for the two outgoing transmission lines is currently undetermined. Subject to the approval of the power grid study , if distance protection is adopted for the lines, Clause 6.2 shall be abolished; if optical differential protection is adopted for the lines, Clause 6.1 shall be abolished.)

6.2

34.5 kV line optical differential protection measurement-control device

Set

5

3 sets for 1# outgoing feeder, 2 sets for 2# outgoing feeder(Note: The protection type for the two outgoing transmission lines is currently undetermined. Subject to the approval of the power grid study , if distance protection is adopted for the lines, Clause 6.2 shall be abolished; if optical differential protection is adopted for the lines, Clause 6.1 shall be abolished.)

附件列表
序号
附件名称
附件说明
操作
1
二次技术规范书(1).zip
下载 预览
附件(1)
utf-8''二次技术规范书(1).zip
下载预览